Using MRP with WO and BOM: My client is noticing MRP is changing req dates earlier then needed for components of the Firm Plan WO . Client normally used FP WO to plan their production and purchasing. They added projections to the FG recently and noticed parent items with both projections and FP are causing the MRP to change Req dates on FP and requiring them much earlier. For instance they created 5 FP WO with due dates for Apr, May, Jun, Jul and Aug . The MRP reflected those require dates for the components. Once they added projections all 5 FP now have req dates of April on the MRP.
Any thoughts on why the MRP is doing this. Are you not supposed have projections and use FP. They normally use one or the other FP or projections, but recently they wanted to use both.