MFG - if your production team is running 3 weeks b

  • 1.  MFG - if your production team is running 3 weeks b

    Posted 02-07-2018 08:07
    MFG - if your production team is running 3 weeks behind schedule and MRP is looking at the dates as the were originally input - does the Push Out change their dates, or is that only designed to push out a work order that isn't needed?


  • 2.  RE: MFG - if your production team is running 3 weeks b

    Posted 02-07-2018 09:01
    it only pushes out work orders that are not needed.


  • 3.  RE: MFG - if your production team is running 3 weeks b

    Posted 02-07-2018 09:40
    @DavidOverholt - had a feeling. Sad face.