I have a client that generates 87 work tickets for a single finished good, with BOMs running about 8 levels deep. They're looking for a solution when a raw material-say at level 5-is going to be delayed.
In my testing with IRP, if I change the PO required date for that raw material to be two months later and then regenerate IRP, the system suggests I pull in the PO. However, it does not recommend rescheduling the impacted work ticket (or the lower-level WTs tied to it).
I'm working on a custom report to handle this, but I'm having trouble getting it to return the results I need.
Has anyone run into this scenario before, and if so, what solution did you implement?
------------------------------