  • 1.  IRP / PM Material Constraint

    Posted 09-29-2025 13:37
    Edited by Andrea Stull 09-29-2025 15:02

    I have a client that generates 87 work tickets for a single finished good, with BOMs running about 8 levels deep. They're looking for a solution when a raw material-say at level 5-is going to be delayed.

    In my testing with IRP, if I change the PO required date for that raw material to be two months later and then regenerate IRP, the system suggests I pull in the PO. However, it does not recommend rescheduling the impacted work ticket (or the lower-level WTs tied to it).

    I'm working on a custom report to handle this, but I'm having trouble getting it to return the results I need.

    Has anyone run into this scenario before, and if so, what solution did you implement?



    ------------------------------
    Andrea Stull | DSD Business Systems
    andreas@dsdinc.com
    ------------------------------



  • 2.  RE: IRP / PM Material Constraint

    Posted 09-30-2025 16:12

    @John Hoyt  @Joseph Bisaha @Joseph Jenders @Jane Scanlan @Madeline Stefanou



    ------------------------------
    Gary Feldman
    Principal
    I-Business Network
    Marietta GA
    16786270646
    http://www-i-bn.net
    ------------------------------



  • 3.  RE: IRP / PM Material Constraint

    Posted 09-30-2025 16:51

    Without attempting any testing, I would be surprised if PM and IRP have that type of interaction and sophistication. I have enough challenges working with the interactions of OM functions - CEM, scheduling, and material constraints. For OM there is code, but we don't have enough documentation to determine what it may be doing.

    No, I have not run into this scenario specifically.



    ------------------------------
    John Hoyt, Co-Founder
    Next Level Manufacturing Consulting Group
    johnh@nextlevelMCG.com
    ------------------------------



  • 4.  RE: IRP / PM Material Constraint

    Posted 10-01-2025 19:09

    OM handles material constraint scheduling. It blows through subassemblies too. It is documented in the OM manual how that works. 

    sorry to be brief. Responding from my phone. 



    ------------------------------
    Jane Scanlan
    Partner
    Next Level Manufacturing Consulting Group
    ------------------------------