Client is trying to move from v2020 with OM to v2023 with PM and IRP. However, we can not get IRP to create PO's correctly, nor to calculate Production demand properly. We have a MAKE item with 12 on hand, 1 on sales order, 12 being made on WT and 7 more being made on WT. If you drill down into the demand it shows (by date); that 0 need to be made. However, it is calculating to Make 6. It is Reorder Point of 30. The six is is suggesting they "make" is not visible anywhere. I have rebuilt sorts (PM, PO, SO, IM); and still it recommends to make 6. If I increase Reorder Point by 2 (from 30 to 32), it then recommends to make 8. The Six (6) it is suggesting comes from nowhere. Screen shot of item maintenance, reorder points, the IRP Recommendation and the IRP Drill down. The first line of that drill down makes no sense. Inventory Quantity = 12, Inventory Balance = 12, Production Qty = 6. I opened a case with Sage but maybe someone here sees what I am missing.
------------------------------
Madeline Stefanou
RKL eSolutions, LLC
------------------------------