    Here's the scenario:  Client wants to update the Standard Price for selective items in a Product Line.  In their world, the Standard Price is a percentage increase over Retail Price (and the percentage varies based on Product Line).

     My vision is to have them utilize a 2-step process:

    1. Use the Automatic Price Change utility to prompt for the product line and reduce Standard Price to $0 for all items in that PL.
    2. Run a VI import job to prompt for the % increase and the PL, then import into Standard Price the new value (e.g. if Standard Price is $1,00 and the increase % is 10%, then import $1.10) into Standard Price for all items in the PL.

    Can this be done using ODBC Data Source instead of importing from a file? 



    ------------------------------
    Barbara Goldstein
    Sr. Consultant
    DSD Business Systems
    San Jose CA
    800.627.9032 x221
    ------------------------------


  • 2.  RE: Import job using ODBC Data Source - can what I want to do be done?

    Posted 10-23-2019 16:48
    bump - crickets chirping.  :-)

    ------------------------------
    Barbara Goldstein
    Sr. Consultant
    DSD Business Systems
    San Jose CA
    800.627.9032 x221
    ------------------------------



  • 3.  RE: Import job using ODBC Data Source - can what I want to do be done?

    Posted 10-23-2019 16:57
    do they value the items based on Standard cost?  Do they use the standard cost field for reporting?  If not, could they re-purpose the Standard cost field for the "retail price" they mark up and use the built-in feature for % markup?

    ------------------------------
    alan niergarth
    Velosio LLC
    ------------------------------



  • 4.  RE: Import job using ODBC Data Source - can what I want to do be done?

    Posted 10-23-2019 17:02
    Their parts use Standard Cost valuation.

    ------------------------------
    Barbara Goldstein
    Sr. Consultant
    DSD Business Systems
    San Jose CA
    800.627.9032 x221
    ------------------------------



  • 5.  RE: Import job using ODBC Data Source - can what I want to do be done?

    Posted 10-23-2019 17:26
    If you add a UDF for the percentage to the PL table, then you could probably come up with something using File Assign temp fields in a calculation... but that seems like a lot of effort, when a spreadsheet can do the same thing a lot easier.  If you need to repeat for a lot of company codes, a custom report to create the spreadsheet could help.

    ------------------------------
    Kevin Moyes
    Technical Systems Analyst
    Munjal White Consulting Co.