  • 1.  I have a customer using Work Order, raw material v

    Posted 05-03-2013 11:02
    I have a customer using Work Order, raw material valuation at standard cost, but actual costs fluctuate. Finished goods are lot valuation for tracking purposes, but they also do reporting on them by standard cost. They are looking for an easier way to do ""what if?"" scenarios on the finished goods standard cost for different values of the raw materials standard cost - right now there are reports they run and dump to Excel, but they are finding it time consuming to manipulate the spreadsheets. This came up when I was talking to them about Inventory Advisor, and they asked if it could do this (which it does not).


  • 2.  RE: I have a customer using Work Order, raw material v

    Posted 05-03-2013 11:39
    Don't know how much easier this is, but had an MD do a little mod for one of my clients where they had a Budget Cost they put on the Item, and the Budget Cost was available in the Cost Roll-up but if you chose Budget Cost as your raw cost, it ONLY rolled up into the FG Budget Cost - did not touch std. Then also had the option of using the Budget Cost on the Costed BOM Report.


  • 3.  RE: I have a customer using Work Order, raw material v

    Posted 05-03-2013 11:49
    I have just been playing with the Cost Rollup Register. Were there issues with it not working correctly on 4.4.03 (multi-bin and mods and reluctant to pay for upgrade)? Because I tried to manually follow through on what it did and its numbers seem way off...


  • 4.  RE: I have a customer using Work Order, raw material v

    Posted 05-03-2013 13:16
    There was a patch for 4.50 for the Cost Rollup Register. I'm not sure if there was one for 4.40.


  • 5.  RE: I have a customer using Work Order, raw material v

    Posted 05-03-2013 17:40
    @PhilMcIntosh could Explore help? Using UDFs for std cost variations you could build a query with the standard cost, UDF cost 1, cost 2, etc. and use a calculation for the scenarios (and export to Excel) or put it in a modified costed bill of material report, formatted to be Excel friendly.


  • 6.  RE: I have a customer using Work Order, raw material v

    Posted 05-04-2013 05:54
    Well, I had a DOH! moment when I realized that of course the BM Cost Rollup was too low - probably it didn't have the labor/burden in it. So I went to the WO Cost Rollup, and it turned $1.57 into $637,504.29. WTF??


  • 7.  RE: I have a customer using Work Order, raw material v

    Posted 05-04-2013 11:04
    Yeah. There was a patch for that.


  • 8.  RE: I have a customer using Work Order, raw material v

    Posted 05-04-2013 13:04
    If the WO Cost Rollup was that high I'd look at the labor rates and routings, and of course a patch as @RobertWood mentioned. Oh and yields too.


  • 9.  RE: I have a customer using Work Order, raw material v

    Posted 05-15-2013 12:13
    4.50.05 had a WO fix: Work order material costs incorrect when the cost completion method was Planned, has been corrected.