Sage 100

 View Only

Getting Rusty: If you have IM, BOM, and MRP, can

  • 1.  Getting Rusty: If you have IM, BOM, and MRP, can

    Posted 06-21-2011 08:36
    Getting Rusty: If you have IM, BOM, and MRP, can MRP suggest purchase orders to replenish Item Stocking levels of components and parent items which are setup with min/max even if you don't have work order? So if I sell a widget that I like to keep 100 minimum and it takes 2 of Item XYZand 4 of Item ABC to make, and I have 50 widgets on hand and run MRP, will it suggest I buy 100 of Item XYZ and 200 of Item ABC?