Just a quick update - Sage sent me a revised JC_JobUnbilledCost_utl.m4p file and a revised JC_RecalcJobToDateCost_utl.m4p file today. They had me rerun all utilities associated with the JC6010/JC6011 fixes in a test company. It backed out all of the extra items that had ended up on the WIP report (about $4,000,000 worth), but now we have reconciliation issues trying to tie back to the GL balance. We're off by about $33,000 and we're trying to work through that since the client usually ties to the penny.
Apparently the original utilities were looking at a billed flag. The subcontractor records themselves had the billed flag set to Y, but the associated PY records didn't so it actually dumped those PY records back to WIP.
------------------------------