  • 1.  For Work Order / BOM aficionados. Costed Bill rep

    Posted 02-26-2016 08:47
    For Work Order / BOM aficionados. Costed Bill report for item =~ $14.69 Cost Rollup from BOM = $.51. What gives?


  • 2.  RE: For Work Order / BOM aficionados. Costed Bill rep

    Posted 02-26-2016 08:48
    there is a routing. when running cost rollup from WO they get $6.00 of labor and $.51 in material instead of $14 in material


  • 3.  RE: For Work Order / BOM aficionados. Costed Bill rep

    Posted 02-26-2016 08:48
    Is there a routing attached to the bill that would increase the WO cost?


  • 4.  RE: For Work Order / BOM aficionados. Costed Bill rep

    Posted 02-26-2016 09:38
    Are cost types same for both reports?


  • 5.  RE: For Work Order / BOM aficionados. Costed Bill rep

    Posted 02-26-2016 09:54
    What Unit of Measure are you using for materials. I have seen issues using fractional Each. I have had to change Each to EA if I am using a fraction of a component


  • 6.  RE: For Work Order / BOM aficionados. Costed Bill rep

    Posted 02-26-2016 11:54
    valuation of the items is standard. using average cost for the rollup selection (same results with last, std or avg). changing some items to EA from EACH did fix previous cost issues. this issue has the BOM cost rollup showing the correct material cost but the WO cost rollup material cost way off on some items. labor seems OK. Sage no help yet. (still waiting on call back)


  • 7.  RE: For Work Order / BOM aficionados. Costed Bill rep

    Posted 02-26-2016 12:07
    Have you tried to roll up and use Standard as the cost, may be a bad average cost of an item.


  • 8.  RE: For Work Order / BOM aficionados. Costed Bill rep

    Posted 02-26-2016 12:39
    yes sir. tried average, last & std with and without intermediate bills. rebuilt keys & sorts in WO & BM. Ran bill validation (pretty clean)


  • 9.  RE: For Work Order / BOM aficionados. Costed Bill rep

    Posted 02-26-2016 13:04
    Alan, I seemed to recall that there was an issue when running the Costed Bill of Materials Report depending on if you were using a Specific Bill verus using a Selection of Bills. The Selection of Bills pulls cost from all levels, give that a try. l


  • 10.  RE: For Work Order / BOM aficionados. Costed Bill rep

    Posted 02-26-2016 13:12
    Something just came to mind, check the components to see if a BOM exists for one of them. If so, the report uses the cost of the BOM instead of the item (even though item may be defined as Buy).


  • 11.  RE: For Work Order / BOM aficionados. Costed Bill rep

    Posted 02-26-2016 13:19
    mystery solved. The bill validation report was showing about two pages of bills with no components. Turns out some of those bills were in fact components of the bills with the whacked out costs.